Going rate for accepting cables for turbines/solar?

Goweresque

Member
Location
North Wilts
What the going rate for taking a connection line from the existing electricity poles that cross ones land to a new wind turbine a mile away or so? My sister and b-in-law have been approached by some neighbours where they farm down in Wales regarding having a connection for a 250kw (I think) turbine put across their farm to the grid (the actual connection being on their farm). Total length across their farm would be 800m, in a duct I assume, though not 100% sure about that.

Is the price dependent on the size of turbine, and could you restrict the use to just the turbine proposed, or would agreeing to one tie you in to any future turbines that might be added on at a later date?
 

MrNoo

Member
Arable Farmer
Location
Cirencester
Without the connection the project would have to source a connection elsewhere, so in effect you can charge what you seem fit I would assume. But being greedy would or could make the project a non starter and hence they'd end up with nothing.
I would guess they would have to sign an option assuming planning not already granted and payment received after planning granted?
I am in a similar situation currently but the other way around, fee agreed for access but they are demanding payment on signing the option regardless of planning being approved or not, making the whole project a no go, so back to growing blackgrass and supporting the chemical companies some more for me!!!
As an aside SSE are planning on putting a cable underground through two of our fields, would say 800m or more and the payment received for this was £1500.
Be interesting to see what others say.
 
Location
Cheshire
What the going rate for taking a connection line from the existing electricity poles that cross ones land to a new wind turbine a mile away or so? My sister and b-in-law have been approached by some neighbours where they farm down in Wales regarding having a connection for a 250kw (I think) turbine put across their farm to the grid (the actual connection being on their farm). Total length across their farm would be 800m, in a duct I assume, though not 100% sure about that.

Is the price dependent on the size of turbine, and could you restrict the use to just the turbine proposed, or would agreeing to one tie you in to any future turbines that might be added on at a later date?

Hi Goweresque, there is no hard and fast rule here and as MrNoo says it is between parties to agree. Often the best rates for cable easements are gained when a developer has no alternative than to go through a single Landlords land.

If we look at the rates that District Network Operators (DNO) pay to do essentially the same thing (put a cable through/over your land) they only pay a few pence per pole or per meter per annum. However this is often forgotten when private schemes are taking place.

A number of factors can play a part when negotiating an easement e.g. distance, location, terms of the easement, etc. However we tell all Landlords to not settle for anything less than a one off £20 to 25/m for a long cable run. If it is a shorter run rates are normally higher due to the effort/hassle in getting an agreement in place. To get the best rates agree a fee on a success basis only. However cases can vary greatly so best to get specialist advice on a particular case.

Negotiating terms of an easement is very hard as ultimately the DNO need to agree to altering their template (rarely achieved). The reason for this is that the DNO normally own any cable outside of a solar farm or turbine site once the plant is commissioned. Therefore there is little point in trying to agree "lift and shift" etc. Your main negotiation point will be on the location of the easement.

A standard easement will not allow for any additional cables to be installed in the future so you shouldn't have issues of further schemes utilising an existing agreement.

We specialise in helping Landlords get the best easement and solar farm rates and terms, so if you want to know more don't hesitate to contact us.

Best,

Tom
Smeaton Wood Energy Ltd
 

Goweresque

Member
Location
North Wilts
Thanks for that. Do I understand it right then that once the cable is installed it becomes the property of the electric co (or National Grid) and it can be used to the maximum of its capacity? Ie if you install a heavier cable than necessary for one turbine, you could then put add additional turbines to it at a later date with no extra fee?
 

kill

Member
Livestock Farmer
Location
South West
A project near me has been offering £10 a metre to go across ground inside a road hedge useing a wheel trencher and are happy to use the road if any one says no!!!
 

Sid

Member
Livestock Farmer
Location
South Molton
Just be aware i've let two neighbours put over and underground cables on my land. Now both object to my project. Lucky they got wayleaves or both would be out forth with! Never letting anyone put anything over or under my land again ever. Will point them in the direction of these two numb skulls when quizzed why!
 
Location
Cheshire
Thanks for that. Do I understand it right then that once the cable is installed it becomes the property of the electric co (or National Grid) and it can be used to the maximum of its capacity? Ie if you install a heavier cable than necessary for one turbine, you could then put add additional turbines to it at a later date with no extra fee?

In theory yes as long is it does not require any further equipment to laid on your land. However obviously the cable costs will increase on the basis that they get planning for more.
 

nickf

Member
Location
Oxfordshire
Just be aware i've let two neighbours put over and underground cables on my land. Now both object to my project. Lucky they got wayleaves or both would be out forth with! Never letting anyone put anything over or under my land again ever. Will point them in the direction of these two numb skulls when quizzed why!
Can you not serve notice on their wayleaves?
 

Goweresque

Member
Location
North Wilts
I don't know..think electric they have a right to pass over? As for private water i don't know.

As far as I understand it, the cables you have given a wayleave for become the property of the Electric Board once the system is accepted by them, and up and running. They don't remain the property of the person developing the energy scheme. Thus they are the same as any other wayleaves for power lines that cross your land. And you can revoke the wayleave for an existing cable or pylon. The Electric Co can then statutorily enforce getting another wayleave, so there isn't much point usually, other than as a lever to get them to do something you want - move a pole out of the way of a new barn for example. The hassle of getting a new wayleave forced through makes them more likely to agree to do what you want.

However in the case of a new wayleave just signed, presumably there will be clauses in it regarding revocation, possibly the landowner has signed them away in return for the cash consideration, or in some way is constrained from revoking the wayleave, for example by having to repay the cash plus interest or suchlike. You should perhaps study the wayleave document you signed to see if there is any way you can revoke the wayleave (were you minded to do so) and thus gain some leverage over your neighbour's objections about your scheme.
 

nickf

Member
Location
Oxfordshire
On a slightly different situation - we bought some land, I own the entrance drive and a neighbour has right of access, in the deeds it states that in return for this right of access that they can never object to any development or planning proposals submitted. I thought it was neat of the solicitor at the time to include this but not sure how or if it is enforceable.

I would always do something like this if I had to grant access or wayleaves.
 

Goweresque

Member
Location
North Wilts
do not be to greedy ,we offered £35 a meter (1000m)plus reinstement costs .He asked for £46 we agreed to this ,Then he change his mind and asked for £65 a meter plus a annual payment of £15000 a year .WE WENT AROUND HIM AND HE HAD NOTHING
(

I think my B-in-L has done a deal at considerably less than £35/m, so hopefully he can't be accused of greed.

However there is another way of looking at large demands for money in such cases, it may not be necessarily be greed (tho it probably is:)), it could be that someone doesn't want the thing in the first place but doesn't want to say no, so pitches the demand high to make you go elsewhere. Some people don't like saying NO and prefer to do it by proxy.
 

renewablejohn

Member
Location
lancs
On a slightly different situation - we bought some land, I own the entrance drive and a neighbour has right of access, in the deeds it states that in return for this right of access that they can never object to any development or planning proposals submitted. I thought it was neat of the solicitor at the time to include this but not sure how or if it is enforceable.

I would always do something like this if I had to grant access or wayleaves.


We have something similar. In our case not worth the paper it was written on. Put in for planning on our agri building and they objected even though not allowed to. Complained and received apology from their solicitors by which time damage had been done with Council made aware of neighbors objection.
 

Alexsmb

New Member
Location
Isle of Coll
As far as I understand it, the cables you have given a wayleave for become the property of the Electric Board once the system is accepted by them, and up and running. They don't remain the property of the person developing the energy scheme. Thus they are the same as any other wayleaves for power lines that cross your land. And you can revoke the wayleave for an existing cable or pylon. The Electric Co can then statutorily enforce getting another wayleave, so there isn't much point usually, other than as a lever to get them to do something you want - move a pole out of the way of a new barn for example. The hassle of getting a new wayleave forced through makes them more likely to agree to do what you want.

However in the case of a new wayleave just signed, presumably there will be clauses in it regarding revocation, possibly the landowner has signed them away in return for the cash consideration, or in some way is constrained from revoking the wayleave, for example by having to repay the cash plus interest or suchlike. You should perhaps study the wayleave document you signed to see if there is any way you can revoke the wayleave (were you minded to do so) and thus gain some leverage over your neighbour's objections about your scheme.
The electricity company owns up to the meter, beyond that it is the consumer. In some schemes it is more cost effective to have a long private line as it can be expensive to get an electricity company to lay cable. I was involved in a discussion over whether to lay a private line or an SSE cable over (well under) my land to get to a community owned mobile mast which I have offered for £1 pa. In the end it was deemed better to spend more on an SSE line as they would be responsible for any problems but this was only possible as it is a government supported project.
 

nickf

Member
Location
Oxfordshire
We have something similar. In our case not worth the paper it was written on. Put in for planning on our agri building and they objected even though not allowed to. Complained and received apology from their solicitors by which time damage had been done with Council made aware of neighbors objection.
That's exactly what I would expect to happen in my situation if I was to apply for change of use. I am not sure how to word these types of clauses to give them more teeth.
 

SFI - What % were you taking out of production?

  • 0 %

    Votes: 102 41.5%
  • Up to 25%

    Votes: 90 36.6%
  • 25-50%

    Votes: 36 14.6%
  • 50-75%

    Votes: 5 2.0%
  • 75-100%

    Votes: 3 1.2%
  • 100% I’ve had enough of farming!

    Votes: 10 4.1%

May Event: The most profitable farm diversification strategy 2024 - Mobile Data Centres

  • 871
  • 13
With just a internet connection and a plug socket you too can join over 70 farms currently earning up to £1.27 ppkw ~ 201% ROI

Register Here: https://www.eventbrite.com/e/the-mo...2024-mobile-data-centres-tickets-871045770347

Tuesday, May 21 · 10am - 2pm GMT+1

Location: Village Hotel Bury, Rochdale Road, Bury, BL9 7BQ

The Farming Forum has teamed up with the award winning hardware manufacturer Easy Compute to bring you an educational talk about how AI and blockchain technology is helping farmers to diversify their land.

Over the past 7 years, Easy Compute have been working with farmers, agricultural businesses, and renewable energy farms all across the UK to help turn leftover space into mini data centres. With...
Top