Grid connection validities were cut back in time scale some years back to prevent developers tieing up large areas and then cherry picking the best.
I think planning consents have at most 3 years if no atart is made, but once granted it can be presumed if should be easy enough to get permission again , unless there has been a big change in the local circumstances,