We lost our place on the grid due to being messed about with developers,ewt should produce a good bit more than the 2 RRB'S and going by the RRB'S in this area i am glad we didn't end up down that route.Roads + crane pad nearly ready,hoping for a quiet January to get the base laid.So you didnt go for the RRBs are you going for 1 turbine or is that 2 rings Is there a better payback with the EWT even after the tarrif drop than going with 2 smaller and getting the higher tarrif
Short road in,had to go in that depth for levels also needed what was dug out to bring up the crane pad levelWhy are they digging so deep for the road?
About 900m most of it is in apart from last 100m or so to the turbineIt looks a good site have you far for the connection
Good stuff, I'm sure you're sooo excited. Our Enercon E48 started producing in Oct, almost 5 years after we started the project. I'm still delirious 2 months later! Imagine what I'm gonna be like when the first FIT cheque arrives!!
Approx 120cu,base doesn't look as big as i thought it would be.Do you know how many cubes of concrete they will need to get the base completed?