Forums
New posts
Forum list
Search forums
What's new
New posts
New resources
Latest activity
Trending Threads
Resources
Latest reviews
Search resources
FarmTV
Farm Compare
Search
Tokens/Searches
Calendar
Upcoming Events
Members
Registered members
Current visitors
New Resources
New posts
Log in
Register
What's new
Search
Search
Search titles only
By:
New posts
Forum list
Search forums
Menu
Log in
Register
Navigation
Install the app
Install
More options
Contact us
Close Menu
Forums
Extras
Computers & IT
FTTP on Demand
JavaScript is disabled. For a better experience, please enable JavaScript in your browser before proceeding.
You are using an out of date browser. It may not display this or other websites correctly.
You should upgrade or use an
alternative browser
.
Reply to thread
Message
<blockquote data-quote="Pheasant Surprise" data-source="post: 6168884" data-attributes="member: 1103"><p>Bout time for some updates on progress....</p><p></p><p>2/4/19:</p><p>Openreach have advised that the jointing has now been completed, we are waiting on the exchange work to be completed now.</p><p></p><p>4/4/19:</p><p>All external jointing works have been completed. We are currently chasing for the exchange work to be completed. Testing of the CBT and Splitter will then follow.</p><p></p><p>11/4/19:</p><p>Openreach advise today that they are currently chasing for the OCR exchange estimate to be completed before jointers can return to site. Underground allocator has assigned an engineer to site today to deal with the exchange work, if successful jointer will be assigned later in the week to complete the testing.</p><p></p><p>Before anyone asks, I have not the foggiest clue what an OCR exchange estimate is or means. Optical something or other I expect. I have asked Cerberus for clarification.</p><p></p><p>Still no closer to knowing when internal cabling and external lead-in from the pole and final end to end commissioning will be completed. At least we’re getting somewhere though.<img src="data:image/gif;base64,R0lGODlhAQABAIAAAAAAAP///yH5BAEAAAAALAAAAAABAAEAAAIBRAA7" class="smilie smilie--sprite smilie--sprite1" alt=":)" title="Smile :)" loading="lazy" data-shortname=":)" /></p></blockquote><p></p>
[QUOTE="Pheasant Surprise, post: 6168884, member: 1103"] Bout time for some updates on progress.... 2/4/19: Openreach have advised that the jointing has now been completed, we are waiting on the exchange work to be completed now. 4/4/19: All external jointing works have been completed. We are currently chasing for the exchange work to be completed. Testing of the CBT and Splitter will then follow. 11/4/19: Openreach advise today that they are currently chasing for the OCR exchange estimate to be completed before jointers can return to site. Underground allocator has assigned an engineer to site today to deal with the exchange work, if successful jointer will be assigned later in the week to complete the testing. Before anyone asks, I have not the foggiest clue what an OCR exchange estimate is or means. Optical something or other I expect. I have asked Cerberus for clarification. Still no closer to knowing when internal cabling and external lead-in from the pole and final end to end commissioning will be completed. At least we’re getting somewhere though.:) [/QUOTE]
Insert quotes…
Verification
Post reply
Forums
Extras
Computers & IT
FTTP on Demand
This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
By continuing to use this site, you are consenting to our use of cookies.
Accept
Learn more…
Top