Wondered about putting this in "What grinds your gears" thread but just wondering how long people are waiting for capital works claims to be paid ???
Did my first claim end of October , £16 k and paid in three weeks from submission , which I thought was very good and a pleasant surprise . Two days later , I submit another claim , £30 k . Got e mail about a couple photos I sent which I replied too and get return e mail to say all good . Its now been 10 weeks and still not paid . Checked two weeks ago on helpline and told its validated just waiting for payment.
Problem is that I have paid out another £55 k for materials , of which £40k is finished and waiting to claim for [only allowed one claim at a time, so in affect they owe me £74k at the moment ] and got £30k of materials coming next week which I will have to pay for in couple weeks time. Oh by the way , only got two years to do the works so the rush is because of THEIR rules !! Getting hacked off with it and still have another £150 k of work to do in next 14 months.
Its all on the scheme they agreed too and timescale is their making so why s it taking so long ???
Did my first claim end of October , £16 k and paid in three weeks from submission , which I thought was very good and a pleasant surprise . Two days later , I submit another claim , £30 k . Got e mail about a couple photos I sent which I replied too and get return e mail to say all good . Its now been 10 weeks and still not paid . Checked two weeks ago on helpline and told its validated just waiting for payment.
Problem is that I have paid out another £55 k for materials , of which £40k is finished and waiting to claim for [only allowed one claim at a time, so in affect they owe me £74k at the moment ] and got £30k of materials coming next week which I will have to pay for in couple weeks time. Oh by the way , only got two years to do the works so the rush is because of THEIR rules !! Getting hacked off with it and still have another £150 k of work to do in next 14 months.
Its all on the scheme they agreed too and timescale is their making so why s it taking so long ???