Colin Lockwood
Member
Hi All,
Some of you will already be aware, but National Grid have brought out new regulations that mandate all G59 relays installed before February 2018 need upgrading – this includes solar, AD, wind turbines, CHP, hydro etc – called the Accelerated Loss of Mains Change Program. The program is designed to get all existing sites updated with regards Loss of Mains (LOM) – the main benefit being to reduce the amount of tripping by relaxing settings within the relay.
Currently, there are grants available that approved contractors can apply for. The grant officially expires on 11th August – so not long now. This may be extended, although there is currently no guarantee. The grant covers ALL COSTS of the work, and does not cost you a penny.
So basically, if you have a G59 relay installed before February 2018 (and if you have a wind turbine, AD plant, CHP plant, batteries, hydro, solar etc you most likely will) you must upgrade it. There are grants available which cover all costs, but these run out shortly.
I work for a company called WindCare. Windcare are an approved contractor with District Network Operators (DNO) across the country and are completing this upgrade works on hundreds of sites across the country on all different technology types.
If the above is something you need to do and we can be of assistance please give me a call. 01751472595 / 07891938955 or email [email protected]
Thanks
Some of you will already be aware, but National Grid have brought out new regulations that mandate all G59 relays installed before February 2018 need upgrading – this includes solar, AD, wind turbines, CHP, hydro etc – called the Accelerated Loss of Mains Change Program. The program is designed to get all existing sites updated with regards Loss of Mains (LOM) – the main benefit being to reduce the amount of tripping by relaxing settings within the relay.
Currently, there are grants available that approved contractors can apply for. The grant officially expires on 11th August – so not long now. This may be extended, although there is currently no guarantee. The grant covers ALL COSTS of the work, and does not cost you a penny.
So basically, if you have a G59 relay installed before February 2018 (and if you have a wind turbine, AD plant, CHP plant, batteries, hydro, solar etc you most likely will) you must upgrade it. There are grants available which cover all costs, but these run out shortly.
I work for a company called WindCare. Windcare are an approved contractor with District Network Operators (DNO) across the country and are completing this upgrade works on hundreds of sites across the country on all different technology types.
If the above is something you need to do and we can be of assistance please give me a call. 01751472595 / 07891938955 or email [email protected]
Thanks