They over run the prescribed time , the 56 days starts on the next full day after they receive the complete application and they have to let you know by day 56 by post if you post it in or take in by hand but can be email if you provide an email address , I suspect they realised thisObtained Q to convert barn to one house, due to cost had to redesign interior so resubmitted it under Q. 56 days from validation (59 days from application) expired yesterday, hadn't heard anything so rang case officer at 4.45 who told us he had approved and would be on the website shortly. At 5.15 he rang agent and said his superior had overruled the approval (not yet refused) and it had been passed to another case officer who is asking for a map of the farm which we are happy to provide. No objections received. Now day 57 can they refuse it now?